HIGH QUALITY CONCRETE & ASPHALT PAVING SERVICES
WE BELIEVE IN DOING THINGS RIGHT THE FIRST TIME
You deserve reliable communication and quality work, and we’re committed to delivering it, day in and day out, as we have for over two decades. With over 6,000 concrete and asphalt projects under our belt, we’ve got the experience to make it happen for you.
CONCRETE
PARKING LOTS
- New Parking Lots
- Full Replacement
- Repairs
- Drives and Approaches
- Sidewalks
- Sidewalk Ramps
- Handicap Ramps
- Curbs and Gutters
- Speed Bumps
- Industrial Ramps
- Pipe Bollards
ASPHALT
PARKING LOTS
- New Parking Lots
- Full Replacement
- Repairs
- Cement Treated Base (CTB) & Overlay
- Overlay
- Full Depth Repair
- Seal Coat
- Crack Seal
- Pot Hole Repair
- Speed Bumps
- Pipe Bollards
CONCRETE CONSTRUCTION
- Trenching
- Interior Slabs
- Small Slab on Grade
- Piers
- Grade Beams
- Pits
- Machine and Utility Pads
- Enclosures/Walls
- Docks and Dock Levelers
- Ramps
- Pipe Bollards
PARKING LOT
MAINTENANCE
Striping and Signage:
- New and Maintenance
- Parking Stalls
- ADA Handicap Stalls
- ADA Handicap Stencils and Signs
- Fire Lane
- Crosswalks
- Ramp Staining
Sealing (Caulking):
- New and Maintenance
- Polyurethane or Hot Rubberized
- Control Joints
- Expansion Joints
- Cracks
- Sidewalks
- Building Expansion Joints
‘GOOD ENOUGH’
ISN’T GOOD ENOUGH
‘GOOD ENOUGH’ ISN’T GOOD ENOUGH
WE’RE ON A MISSION TO PROVIDE
MORE THAN EXCEPTIONAL PAVING SERVICES
It’s our goal to consistently provide you with a higher level of service and transparency on every project we take on.
COLT STANDARD
METHODS AND MATERIALS
WE’RE COMMITTED TO DELIVERING
CONSISTENTLY HIGH QUALITY WORK
Concrete
Demolition
Existing pavement, curb and sidewalk needing removal will be saw-cut into sections/blocks or perimeter cut and demolished using breaker/hammer and then removed by appropriate equipment. Concrete slurry resulting from concrete saw operation will be vacuumed and removed from site. All materials removed during demolition will be removed from site.
Subgrade Preparation
Subgrade will be excavated as needed and either FlexBase for pavement/curbs or a Fine Grade FlexBase for sidewalks will be added & compacted as necessary to ensure desired compaction/surface preparation is achieved & lines are brought to the required grades for placement of new concrete.
Expansion and Control Joints
- Expansion Joints
Redwood will be placed from subgrade to pavement grade and spaced as needed or to match existing. A felt-based expansion material will be against existing slabs/foundations. - Control Joints
In pavement will be green-sawed at 15’ intervals or to match to existing; sidewalks will be troweled at intervals equal to width or to match existing. Note: All joints will be sealed to match existing.
Note: All joints will be sealed to match existing.
Concrete Material
All drive, curb and sidewalk paving shall be designed to have a minimum compressive strength of 3,500 psi at twenty-eight (28) days and placed at a depth of 5” for sidewalk, 6” for pavement and 12” for curbs. Concrete will have a camel hair broom finish. Note: A curing compound will be applied during the hot months of the year (with daily temperatures exceeding approx. 90°) to protect it from drying out too quickly resulting in a weaker finish with higher tendencies toward cracking and spalling.
Steel Specifications
- Paving and Sidewalk
No. 3 deformed domestic rebar placed on 18” centers each way. - Curb
3 continuous lines of No. 3 deformed domestic rebar. - Expansion Joints
No. 3 deformed domestic rebar dowels 24” long placed on 18” centers and located at mid-depth. - Longitudinal Butt Joints (into existing paving)
No. 3 deformed domestic rebar dowels 20” long placed on 18” centers, located at mid-depth and drilled 8” into existing pavement.
Asphalt
Overlay
Clean existing area with “Power Broom” and/or “Billy Goat” as needed. Apply a tack coat over entire surface area. Install 2” of Hot Asphalt Type “D” topping. Roll to compaction with a steel wheel vibratory roller.
Full-depth
Perimeter of area to be saw cut & removed to a depth of 6” and sub-grade compacted. Tack and install a 4” binder base of Hot Asphalt Type “B” followed by a topping base of Hot Asphalt Type “D” rolled with steel wheel vibratory roller to a compacted depth of approx. 2” and flush with adjacent gutter.
Cement Treated Base (CTB) & Overlay
Existing asphalt to be pulverized to a depth of 9” adding 6″ of Portland cement by weight finishing with water & compaction to depth of 6”. Tack coat to be placed over entire surface of newly prepared subgrade. Hot asphalt type “D” will then be placed and rolled with steel wheel vibratory roller to a compacted depth of approx. 2”.
Sealcoat
Clean existing area with “Power Broom” and/or “Billy Goat” as needed. Treat areas of petroleum saturation & prime with a heavy-duty bonding agent to promote surface adhesion. Apply 2 coats of Coal Tar Pitch Emulsion protective coating at 1 gallon per 45 sq. ft. Six pounds of sand to be added per 1 gallon of coal tar. GemSeal Fed/Spec Pavement Sealer will be mixed at 4 gallons per 100 gallons of coal tar.
Barricades & Safety
All exterior construction areas will be adequately closed off with barricades, pylons or yellow caution tape. Barriers around new concrete pavement and curbs will remain in place for 5 days; new concrete sidewalks 24 hours; new asphalt pavement 3 days to ensure material is fully cured for traffic.
Barricades & Safety
All exterior construction areas will be adequately closed off with barricades, pylons or yellow caution tape. Barriers around new concrete pavement and curbs will remain in place for 5 days; new concrete sidewalks 24 hours; new asphalt pavement 3 days to ensure material is fully cured for traffic.
Colt provides concrete and asphalt paving projects & repair services to commercial/retail/industrial property managers, owners and general contractors in the greater Dallas/Fort Worth area.